We are highly familiar with policy trends and government regulations that affect infrastructure projects as well as the critical commercial needs and interests of our infrastructure partners and clients. Our business plan includes the goal of further developing our capability in this sector. Capitalising on our recent award-winning work, we will continue to enhance our design expertise and develop even greater specialist knowledge of industry and construction trends across this sector.
Our most recent projects include:
Kogarah Sub Station (2009)
$8.7 million
This project consisted of the construction of a 132/11/kV Zone Substation and was part of a major Energy Australia programme to improve overall energy supply to this region.
Chanel 9 Network Substation, Artarmon (2007)
$2.5 million
Scope of works involved the construction of a new transformer fully switched distribution Substation.
Caltex Odourant building, Kurnell (2007)
$0.5 million
Construction of an Odourant building in a high security area at the Caltex Refinery site at Kurnell.
Frenchs Forest Carpark, Macquarie Goodman Group (2007)
$7.4 million
A staged construction of a new suspended car park level over an existing operational loading dock. This project was constructed in a busy industrial estate, with the loading dock area utilised 24 hours per day, five days a week by the Target retail chain.
West Ryde Substation (2010)
$0.7 million
A new Substation providing a power supply system to run trains in the Sydney Metropolitan Area for Railcorp. One of many substations to be built to meet the growing electrical demand created by the increased number of air-conditioned trains and peak hour services planned for the future timetable. The new building contains complete structural elements, amenities and ventilation for the electrical equipment.